New Shop Track Construction
Phase II: 2005/06

Phase II of the shop track project began in October 2005. Excavations picked up where they left off in 2004.

img

Excavating toward the shop.

img

Several feet of parking lot was removed, but the new tracks will still run uphill from the passing siding to the shop.

img

By the end of October the excavations were complete and the new grade is ready for ballast and ties.

In conjunction with the shop track project, the north end of the pit track was ripped out and excavated in preparation for new ballast and ties. Note the lop-sided groundhog-infested shed in the foreground. It will soon be removed to the wood pile for locomotive fuel.

img

The north end of the pit track has been excavated in preparation for new ballast and ties.

Most of November focused on installing related storm drain lines and utilities. The shop received several concrete jack pads. The pads will be hidden under the new west-side shop track and will provide a solid foundation for jacking equipment. The north end of the pit track was reinstalled and was mostly complete by the beginning of December.

img

The pit track was re-laid with new ballast and ties by end of winter.

img

By April 8, 2006, the final switch was taking shape in front of the building.

img

On April 30, 2006 the west-side track was laid into the shop and MOW equipment was run into the shop for the first time.

img

By May 7 enough tamped ballast had been added to run the first piece of non-MOW equipment into the shop. WK&S #7258 got the honor.

img

#65 is first up for some indoor maintenance.

img

Coach #1474 is in for repairs. Note the new concrete pads supporting the crane and other equipment. The forklift is parked where the second east-side track will soon be built.

Over the Thanksgiving weekend WK&S volunteers completed the east-side track into the shop. The new track was put to immediate use. As shown below, combine #408 was pushed inside to load the baggage compartment with gifts and snacks for the upcoming Santa Claus Specials. This marks the end of track construction although the entire project will still require some minor ballasting, tamping and surfacing.

img

Both new shop tracks are inservice.

A few loose ends were put off as more pressing projects were tended. During the summer of 2008 the old timber retaining walls around the pit were replaced with concrete block.

img

Finishing up the pit.